Bryan Boilers EB Series User Manual

EB Series  
Steam Boilers  
Forced Draft - Gas, Oil, Gas/Oil  
The boiler shall be a Bryan Model ___________  
flexible water tube water boiler, with a capacity of  
______ BTU input and ______ BTU output.  
(__________HP)  
FURNACE/COMBUSTION CHAMBER  
CONSTRUCTION  
Access to the furnace/combustion chamber is  
gained by a hinged access door(s) with an  
opening of no less than 26" wide x 62" high  
maximum to allow for inspection of the interior  
chamber and the burner head. All remaining  
panels shall be individually removable. All  
access panels shall be affixed to the pressure  
vessel frame and insulated with 2” mineral fiber  
mono block and 2” high temperature ceramic  
blanket insulation and be fully gasketed for  
pressurized firing.  
The boiler shall be constructed and assembled  
as a completely packaged unit ready for field  
connections to the steam supply, return  
connection, electrical power supply, fuel  
supply(s), relief valve discharge, building  
management controls and flue-gas vent.  
15 PSIG STEAM BOILERS - The boiler shall be  
manufactured in strict accordance with the  
ASME Low Pressure Boiler Heating Code,  
Section IV, and shall bear the ASME “H” stamp  
for a maximum working pressure of 15 PSIG.  
The furnace/combustion chamber shall be  
primarily of water-wall design with one side of  
removable panels. The stationary interior wall  
shall be lined with 1” mineral fiber mono block and  
1” ceramic blanket insulation. The front and rear  
walls are insulated with 4” mineral fiber mono  
block and 2” ceramic blanket. The floor beneath  
the tubes shall be lined with 2” mineral fiber mono  
block insulation and 2” ceramic blanket. The  
boiler furnace/combustion chamber and flueways  
shall be designed to operate at a positive 0.50”  
w.c. at the boiler flue outlet. The boiler will require  
a “positive pressure” type metal flue.  
150 PSIG STEAM BOILERS - The boilers shall  
be manufactured in strict accordance with the  
ASME Power Boiler Code, Section I, and shall  
bear the ASME “S” stamp for a maximum  
working pressure of 150 PSIG.  
(Also available for higher pressures up to 250  
PSIG and temperatures to 300oF.)  
VESSEL AND TUBE CONSTRUCTION  
JACKET CONSTRUCTION  
The boiler shall be constructed on a heavy steel  
frame. The boiler pressure vessel shall be  
provided with adequately sized upper and lower  
drums. A minimum of two downcomers shall be  
provided and shall be located inside the furnace  
chamber to maximize proper thermal internal  
water circulation. The boiler steam drum shall be  
no less than 24” O.D.. The drum shall be  
provided with internals designed for providing  
steam quality in excess of 99%. Steel water  
tubes are to be 1½” O.D., .095 wall thickness  
minimum, six-pass, flexible serpentine bend  
design, not subject to thermal shock damage.  
Individual water tubes shall be easily removable  
and replaceable without either welding or rolling.  
The boiler shall have no more than two tube  
configurations. The boiler shall be furnished with  
an adequate number of tappings and inspection  
openings to facilitate internal boiler inspection and  
cleaning.  
The boiler shall be complete with a metal jacket,  
16 gauge, zinc-coated rust resistant steel casing,  
finished with a suitable heat resisting paint and  
shall be constructed on a structural steel frame  
and properly insulated with no less than 1½”  
fiberglass insulation. Complete jacket and  
insulation shall be easily removable and  
reinstalled. The boiler shall incorporate  
individually removable jacket doors, with handles  
providing easy access to combustion chamber  
and access panels. The entire tube area shall  
be easily accessible for fireside cleaning.  
All appropriate controls, where possible, shall be  
mounted on boiler front.  
A tube removal and replacement shall be  
demonstrated at time of start-up. Demonstration  
time not to exceed 40 minutes.  
The boiler vessel shall be warranted for 25 years  
against thermal shock on a non-pro-rated basis.  
(Continued on Page 2)  
Form 2127  
 Rev 07/01/06   Repl 11/01/04  
Page 1 of 2  

Allied International GX1050C User Manual
Black Decker BLM10600G User Manual
Bunn Beverage Dispenser 2SH User Manual
Bushnell Binoculars 20 1925 User Manual
Bushnell Syncfocus 118326 User Manual
Casio Graphing Calculator FA 9860 BV2 0 User Manual
Focal 6 KRXS User Manual
JBL Grand Touring GTO636 User Manual
JL Audio C3 570 XO User Manual
JVC CAMESCOPE GR DVL100 User Manual